Move Update – 4 Oct 2016

Work is well underway for our exciting move in 2017.

Our move chairman, Alan Brooking, gives us an update on how things are progressing:

  • The grass on the 1 XV pitch are starting to come through and pitch 2 and mini pitches have been seeded
  • Pitch 3 and 4 seeding is on hold until next week whilst water works inspection chamber is to be complete
  • 30,000 litres of water for the irrigation have been put into water tank, pump has been installedand is waiting for a connection to the supply
  • Floodlights for all the pitches are now up
  • Hedges have been scrubbed out, and emergency track is in the process of being created
  • Landscaping around 1 XV pitch, pitch 2 and mini pitches has been completed and approx 50% has been seeded
  • The car park levels have been cut
  • Final preparations for the clubhouse are being completed so ground floor block can be cast later this week
  • An agreement has been signed for a BT connection can be installed
  • The land to next to pitch 4 will be leveled in the coming week and  covered with the spare top soil, de-stoned and seeded and there will be enough space for 2/3 additional mini training areas.

These are exciting times for the Club, if you are interested in joining, volunteering, sponsoring the club or are a community club looking for a new home then please contact, Alan Brooking on 07764 563352

 