Move Update: 20 Feb

92 days until completion:

Week 33 of 46 and there are now over 50 people now working on site covering all areas:

  • Main car park and blocks are complete
  • Access road, finished, to second level, final finish will not bet applied till May
  • Insulated panels in situation
  • Ground Floor External Masonry Walls are complete
  • Plant Room boilers, tanks, pumps all in situation
  • Ground Floor, blockwork, 80% complete
  • Electrical first fit started in ground floor
  • First Floor, stud work commenced
  • Work stated on supporting structure for ramp
  • Meeting with Huttons, F&W & Green King to finalise bar details, some minor changes to bar back shelve layout and lighting plan
  • Meeting held with F&W, re service points and equipment locations, some minor changes including moving the boot cleaner from the west end of the building to the East, so we now have both units closer to egress points and external supply to Terrace has been moved from the kit room to outside for easier access and use
  • Meeting held with F&W and Alarm and CCTV contractor, some minor changes to control access
  • Meeting held with Huttons, F&W and Dcad, re AV, PA, Wifi and speaker locations
  • Car Park Bollards. agreed change of design , savings 50K.

Key elements for completion over the next 2 weeks:

  • Steps to east pitches
  • Installation and connection of Power Supply
  • Water Connection
  • Gyproc Walls in Changing Areas
  • Commence Members Car Park
  • Complete Thames Water sewer works between pitches 3 & 4
  • Roof Coverings and Fascias
  • Sub Surface Scan – Ram Gorse
  • Stadet Geo works on Ram Gorse.